Reports: Belarusian NPP launch may be delayed by one year 1 234 567

Reports: Belarusian NPP launch may be delayed by one year

euroradio.fm

The Belarusian NPP may be launched 10-12 months later than planned, an anonymous energy market exprt told Interfax. The Russian state corporation Rosatom may have to give Belarus the power unit meant for Leningrad NPP-2 that is also being built now. It is ‘in a state of better readiness’. The incident at the building site of the Belarusian NPP occurred on the night of July 10 but was reported in mass media much later. A reactor was being transported at the height of four metres when the crane broke down. The reactor was hanging in the air gradually descending for 30 minutes until it ‘touched the ground’. The...